We would like to inform the community of the planned construction activities on Durham Rd, Gresford, from March 18 to March 22, 2024.
Here's a breakdown of the scheduled activities:
* Import base course material
* Trim and shape
* Concrete driveways and footpath installations
Tuesday 19th March:
* Pavement stabilisation
Wednesday 20th March:
* Pavement stabilisation
Thursday 21st March:
* Pavement Curing
Friday 22nd March:
* Bitumen Seal CH25-400
Please note that the construction activities scheduled for this coming week are highly sensitive to weather conditions, particularly wet weather. Unfortunately, the forecast for the coming week predicts unsettled weather, with showers likely on most days
.
These scheduled activities will also impact residents' access to their properties. The Contractor will directly liaise with affected residents throughout this period to minimise disruptions.
Additional Traffic Control measures will be implemented during pavement stabilisation and sealing operations.
During these works, access to Gresford Garage & Rural will be restricted. We are consulting with and working closely with the Garage to minimise impacts on their business as much as possible.
We apologise for any inconvenience caused by these necessary works and sincerely appreciate your cooperation and patience during this time.
/Public Release. This material from the originating organization/author(s) might be of the point-in-time nature, and edited for clarity, style and length. Mirage.News does not take institutional positions or sides, and all views, positions, and conclusions expressed herein are solely those of the author(s).View in full here.