Durham Road Construction Works Notice
As part of our commitment to improving the infrastructure in our community, we'd like to inform you of the work scheduled to take place for the week of July 15th to July 19th .
Here's what to expect:
Monday 15th July – Subgrade and pavement works.
Tuesday 16th July – Subgrade and pavement works.
Wednesday 17th July – Switch traffic and commence milling of existing pavement.
Thursday 18th July – Mill existing pavement.
Friday 19th July – Subgrade treatments.
These activities will affect access to residents' properties. The Contractor will be in direct communication with affected residents throughout this period. If you have concerns regarding driveway access, please reach out to Council and request to speak with the project manager.
Please note that these construction activities are extremely sensitive to weather conditions, especially wet weather, which may affect the contractor's ability to carry out certain tasks.
Looking ahead to the week of July 22nd to July 26th, the forecast construction program has the contractor installing subsoil drainage and importing pavement materials
Thank you again for your cooperation and patience as continue to carry out these essential works.