As part of our commitment to improving the infrastructure in our community, we'd like to inform you of the work scheduled to take place for the week of May 6 to May 10.
Here's what to expect:
Monday 6th May – Sub base preparation for concrete works.
Tuesday 7th May – Sub base preparation for concrete works.
Wednesday 8th May – Sub base preparation for concrete works.
Thursday 9th May – Concrete works
Friday 10th May – Concrete works
These activities will affect access to residents' properties. The Contractor will be in direct communication with affected residents throughout this period. If you have concerns regarding driveway access, please reach out to Council and request to speak with the project manager.
Please note that these construction activities are extremely sensitive to weather conditions, especially wet weather, which may affect the contractor's ability to carry out certain tasks.
Looking ahead to the week of May 13 to May 17, the construction program has the contractor importing base course and preparing for final trim.
Thank you again for your cooperation and patience as continue to carry out these essential works.
/Public Release. This material from the originating organization/author(s) might be of the point-in-time nature, and edited for clarity, style and length. Mirage.News does not take institutional positions or sides, and all views, positions, and conclusions expressed herein are solely those of the author(s).View in full here.