The EnergyConnect project team are continuing to advance construction activities on the transmission line from Buronga to Dinawan near Bundure, NSW. As part of this work, Elecnor is expanding its accommodation camp at Dinawan to increase its workforce on construction activities in the area.

From mid-March 2025, there will be an additional 80 beds at the Dinawan camp, increasing occupancy at the camp to 463 beds, which will remain in place for the duration of the project. These additional temporary accommodation buildings will be transported to the Dinawan site from the project's existing construction camp at Buronga.
The approved standard hours for construction activity and laydown operations are:
• 7am to 6pm Monday to Friday
• 8am to 1pm Saturdays
• At no time on Sundays and NSW Public Holidays
You can expect to see the transportation of accommodation units by heavy on Arumpo Road, Buronga, and the Sturt Highway as these travel from the Buronga camp in the Wentworth LGA to the Dinawan camp in the Murrumbidgee LGA.