Fukushima Soil Plan Safe, IAEA Confirms

Japan's approach for recycling and disposing of soil and radioactive waste from decontamination activities after the 2011 Fukushima Daiichi Nuclear Power Station (FDNPS) accident as currently planned is consistent with IAEA Safety Standards, an International Atomic Energy Agency (IAEA) report released today says.

The findings, presented by the IAEA to Japan's Minister of the Environment Shintaro Ito today, were the result of a sixteen-month safety review. The IAEA assessed the approach of the Ministry of Environment Japan (MOEJ) to date for the managed recycling and the final disposal of removed soil and radioactive waste against the IAEA Safety Standards. These safety standards serve as a global reference for protecting people and the environment and contribute to a harmonized high level of safety worldwide.

"We appreciate the enormity of the challenge facing Japan in dealing with the aftermath of the 2011 FDNPS accident and we commend the country for requesting our impartial and technical review of its plans," said IAEA Director General Rafael Mariano Grossi. "The recycling and disposal of the soil further contributes to the reconstruction of areas affected by the accident."

About 13 million cubic meters of soil and about 300,000 cubic meters of ash from incineration of organic material was removed as part of decontamination activities in Fukushima Prefecture and stored at an Interim Storage Facility (ISF) covering an area of 16 square kilometres, spanning across the Okuma Town and Futaba Town.

The management of removed soil-enough to fill 11 Tokyo Domes-is governed by a Japanese law which permits the government to repurpose the soil both within and outside of Fukushima Prefecture and for final disposal of the remaining soil to take place outside of the Fukushima Prefecture by 2045.

Japan plans to recycle roughly 75% of the removed soil - the soil which has low levels of radioactivity - by using it, if demonstrated safe, for civil engineering structures including embankments for roads, railways, seawalls, waste treatment sites, coastal protection, agricultural land, and land reclamation. The remaining soil which cannot be recycled will be disposed of permanently and Japan intends to confirm the site selection and disposal process in 2025.

"The IAEA is confident that as the Ministry of the Environment (MOEJ) continues to explore solutions in line with our recommendations, its evolving strategy for recycling and final disposal of removed soil and waste will remain consistent with IAEA Safety Standards," said Director General Grossi.

In response to Japan's request in October 2022 for a safety review, an IAEA team - comprised of five IAEA staff and six international experts from Belgium, Germany, Japan, the UK, and the US - conducted three international expert missions in May 2023, October 2023 and February 2024. The IAEA's review included providing advice and support to Japan from both technical, including safety aspects, and social viewpoints.

The team of experts recognised the many technical and social challenges facing the MOEJ if it is to implement the managed recycling of removed soil and secure final disposal outside Fukushima Prefecture by 2045.

"The IAEA found the MOEJ's proactive approach to managing removed soil and waste arising from decontamination activities reflects a commitment to ensuring safety, protecting public health and promoting environmental sustainability in Fukushima Prefecture and beyond," said Director General Grossi. "The IAEA is committed to engaging with Japan on the managed recycling and the final disposal of removed soil and waste through future follow-up assessments of the MOEJ's approach."

/Public Release. This material from the originating organization/author(s) might be of the point-in-time nature, and edited for clarity, style and length. Mirage.News does not take institutional positions or sides, and all views, positions, and conclusions expressed herein are solely those of the author(s).View in full here.