Phase 1 of Molong Town Centre's Stage 2 Activation Complete

molong main street photo.jpeg

Stage 2, Phase 1 of the Town Centre Activation Plan has been completed, and Phase 2 will start on Thursday 4 April 2024 and is expected to be complete week commencing 3 June 2024.

Works will start on the Gasworks Lane area on Monday, 4 March 2024 for approximately 4 weeks (subject to weather conditions) and will have no impact on Bank Street. This will include:

  • New carpark area for long vehicles, and/or long-term parking
  • Creates connectivity between swimming pool and oval precinct back to Gasworks carpark area.
  • Will include some drainage improvements at site.

Access to rear of Bank Street businesses will be via lane near Molong Caravan Park and Molong Tyre and Mechanical.

Stage 2 update (10)_1.jpg

FAQS

WHAT IS THE TIMELINE FOR STAGE 2, PHASE 2?

Stage 2, Phase 2 of the Molong Town Centre Activation Project encompasses the top end of Bank Street, (as shown in the diagram on the first page). The expected timeline for this section of works is approximately 9 weeks with works commencing Thursday, 4 April 2024 through until the week commencing Monday, 3 June 2024. Subject to weather conditions, it is hoped that all works will be completed prior to the June long-weekend.

WHY HAVE THE DATES CHANGED FOR THE COMMENCEMENT OF PHASE 2?

Stage 2, Phase 1 is ahead of schedule due to the efficiency of contractors and favourable weather conditions. It is possible that weather conditions for the Phase 2 works could cause delays, however regular updates will be provided throughout the works to keep the community notified on the progress - including of any delays.

CAN I ACCESS THE GASWORKS LANE CARPARK?

Access to Gasworks Lane from the Mitchell Highway (Opposite the Pool) will be closed from Monday, 4 March 2024 to Monday, 1 April 2024 for a period of up to 4 weeks to allow for earthworks and concreting works associated with the Gasworks Carpark.

Access to the Gasworks Lane carpark and the rear of the business's will still be possible from the Mitchel Highway (Caravan/Mechanics entrance).

WILL THERE STILL BE PARKING AVAILABLE ON THE STREET?

Parking will be available on Bank Street throughout the project, with parallel parking available across from the work area. However, there will be no parking in the designated work area. Access will be maintained for residents during the construction timeframe.

Council has undertaken testing to ensure that the design will meet the requirements of users (including motorists and pedestrians) and ensuring that parking is accessible for a range of vehicle types. This has been further proved through the delivery of the project in the top block of Bank St (from Gidley St to Edward St).

Once the project is complete the parking spaces will be wider than the minimum requirements, and line markings will be added to the road to assist people to adjust to the 45-degree angled parking. The removal of the existing trees will also result in additional carparks, not less.

WILL DELIVERIES STILL BE POSSIBLE ON BANK STREET DURING THE WORKS?

Yes, deliveries will be possible for businesses during all stages of the construction works. Delivery vehicles will be able to park either in the 45-degree angled parking, or between tree plantings in the street centre, once they are installed.

To view this information in a PDF, click here(PDF, 2MB)

For more information about the Molong Town Centre Activation Plan click the link below.

/Public Release. This material from the originating organization/author(s) might be of the point-in-time nature, and edited for clarity, style and length. Mirage.News does not take institutional positions or sides, and all views, positions, and conclusions expressed herein are solely those of the author(s).View in full here.