Q2 Metals Expands Drilling at Cisco Lithium Project

Q2 Metals Corp.

Highlights

  • The 2025 Winter Drill Program is fully funded and anticipated to commence February 1, 2025.

  • The 2025 Winter Drill Program is targeting 6,000 - 8,000 metres ("m") of drilling using two diamond drill rigs.

  • The primary objective is to continue to expand upon the exceptional drill results from the 2024 drill campaign.

VANCOUVER, BC / ACCESS Newswire / January 20, 2025 / Q2 Metals Corp. (TSX.V:QTWO)(OTCQB:QUEXF)(FSE:458) ("Q2" or the "Company") is pleased to announce that the 2025 Winter Drill Program (the "2025 Winter Program") at its Cisco Lithium Project (the "Project" or the "Cisco Project") is anticipated to begin on February 1, 2025. Crews will be mobilizing to the Cisco Project over the course of the next week.

The primary objective of the 2025 Winter Program is to continue to expand upon the exceptional drill results from the 2024 drill campaign which included:

  • Drill hole CS-24-018 - 215.6 m at 1.69% Li2O

  • Drill hole CS-24-021 - 347.1 m at 1.35% Li2O; and

  • Drill hole CS-24-023 - 188.6 m at 1.56% Li2O

Alicia Milne, Q2 Metals President and CEO commented: "We are excited to get back to work on the Cisco Project to continue to reveal its true potential and look forward to unlocking further value for our shareholders as we expand on the known mineralization zone by stepping out into untested areas of the Project."

"Since completing the 2024 Drill Program, our team has been evaluating all of the data that was collected to gain a better understanding of what we're seeing at Cisco," stated Neil McCallum, Q2 Metals VP of Exploration. "We have several highly promising targets that we are eager to explore to better understand the extent of Cisco."

The 2025 Winter Program is planned to continue until mid-April 2025, targeting 6,000 - 8,000 m of drilling. Once the program begins, systematic drilling will be carried out with step outs between 200 and 400 m apart (Figure 1 and Figure 2).

Figure 1. Map showing 2025 Winter Program drill targets

One diamond drill rig will test to the southwest of drill hole CS-24-023 to define the strike length, and the other drill rig will test to the east of drill hole CS-24-018 and CS-24-021 to define potential additional parallel pegmatite zones.

Figure 2. Long Section containing all holes drilled to date (looking southwest)

Upcoming Events:

AME Roundup Core Shack

Q2 is pleased to have been selected as a participant in the core shack at the upcoming AME annual Roundup conference being held in Vancouver, BC from January 20 - 23, 2025.

Vice President of Exploration Neil McCallum as well as senior project geologists will be on hand with core from the 2024 drill season at Cisco. Mr. McCallum will also be presenting at the Critical and Base Metals Speaker Session on Tuesday January 21, 2025.

/Public Release. This material from the originating organization/author(s) might be of the point-in-time nature, and edited for clarity, style and length. Mirage.News does not take institutional positions or sides, and all views, positions, and conclusions expressed herein are solely those of the author(s).