Rio Tinto Issues Iron Ore Update Post-Cyclone Sean

Tropical Cyclone Sean delivered record rain along parts of the Pilbara coastline of Western Australia, impacting Rio Tinto rail and port operations.

A railcar dumper at the East Intercourse Island (EII) port facility, which shipped 45 million tonnes of total Rio Tinto Iron Ore shipments in 2024, was flooded after the weather event passed the coast, delivering 274mm to Karratha during 20 January 2025.

Assessments are ongoing. Initial indications suggest the dumper at EII could be offline for three to four weeks, as rectifications works are required to repair flood damage.

Recovery works within the broader Iron Ore system are progressing, with the majority of rail and port operations now returned to operations.

The company is working to mitigate impacts and will provide an update at its full year results on 19 February 2025.

First quarter shipments will be affected. Overall shipment guidance for 2025 remains unchanged.

/Public Release. This material from the originating organization/author(s) might be of the point-in-time nature, and edited for clarity, style and length. Mirage.News does not take institutional positions or sides, and all views, positions, and conclusions expressed herein are solely those of the author(s).View in full here.