The Rockliff Liberal Government is getting on with the job of delivering on our significant investment to upgrade the Launceston General Hospital, through our $580 million 10-year redevelopment plan.
Minister for Health Guy Barnett said: "As our Implementation Programme outlines, Stage 2 (2022-24) includes planning for the purpose-built mental health precinct and site preparation.
"Stage 3 (2024-27), will feature a series of major construction projects, including the new mental health services precinct, an expanded and redesigned acute care zone, a new medical inpatient unit for older persons and a new carpark.
"The detailed planning for the construction of a new inpatient and outpatient tower will also begin, ahead of construction in Stage 4 (2027-34).
"Funding in line with the Implementation Programme has been allocated in this year's budget.
"This is real investment, unlike Labor's pie in the sky thought-bubbles that they laughably claim will 'pay for themselves', which is clearly absurd.
"I am also engaging with the Federal Government about its role in supporting this important redevelopment.
"It says everything that Labor attacks the fact we have a long-term plan for the LGH.
"This Government is totally focused on delivering the modern healthcare facilities Tasmanians need."
LGH Masterplan projects already delivered:
- Completion of Paediatric Ward redevelopment (June 2021)
- Opening of new 38 bed medical ward 3D (September 2021)
- Nine Negative Pressure Rooms in Acute Medical Unit (August 2022)
- Fit-out of the paediatric outpatient area on Level 3 of the LGH Women and Children's tower (September 2022)
- Fit-out of the Women's Health Clinic on Level 5 of the Women and Children's Tower (October 2022); and
- Complete refurbishment of the 39 Frankland Street Administration and Education Precinct (September 2022).
- Improvements to the Emergency Department Ambulance Bay are also due for completion mid-September 2023